year=2008
month=2
day=31
hh =[ year month day ]
datetime(hh) %it's not correct ((correct day is 31 not 2)
%i try to change datetime default but the result is the same
datetime.setDefaultFormats('defaultdate','yyyy-MM-dd')
datetime(hh)
0 Comments
Accepted Answer
Angelo Yeo
on 22 Sep 2023
There was no Feb 31st in 2008.
4 Comments
Walter Roberson
on 22 Sep 2023
It is a common trick to code datetime([year 1 daynumber]) instead of datetime([year 1 1])+days(daynumber-1)